Cascade Land Services LLC — a fictional firm, standing in for yours
Individual Scope of Work
Regulator Station Power Drop — Land Services
1. Project understanding
Granite Basin Power & Gas requires land-services support for a power drop to an existing regulator station. The work involves a conduit run of approximately 60 feet between two tie-in points, crossing a parcel preliminarily identified as town-owned. The requesting engineer anticipates three to five permits and a temporary use agreement for construction parking. This scope covers the land, permitting, and access work required to clear the corridor for construction; it does not include construction itself.
2. Scope of services
Task 1 — Permit applications (4), through issuance. Prepare, submit, and track municipal and right-of-way permit applications associated with the conduit run and station work, including responses to reviewer comments, through issuance. Priced at four applications; the basis for that count is stated in Section 4.
Task 2 — Landowner coordination, town parcel. Confirm ownership of the crossing parcel through the county record, identify the responsible municipal department, and coordinate consent for the crossing, including meeting attendance and written follow-up until consent is documented.
Task 3 — Temporary use agreement, construction access and parking. Draft and negotiate a TUA covering construction access and equipment parking for the duration of construction, on the utility's standard TUA form, executed before mobilization.
Task 4 — Title review and mileage. Title review of the affected parcel to confirm the record owner and any encumbrances bearing on the crossing, plus field mileage associated with the tasks above.
3. Pricing
| Task | Basis | Amount |
|---|---|---|
| 1. Permit applications ×4, through issuance | Rate sheet rev. C, unit price per application | $4,320 |
| 2. Landowner coordination, town parcel | Rate sheet rev. C, coordination rate | $2,240 |
| 3. TUA, construction access & parking | Rate sheet rev. C, agreement rate | $1,610 |
| 4. Title review & mileage | Rate sheet rev. C, title unit + mileage schedule | $2,140 |
| Total, not to exceed | $10,310 | |
All pricing from rate sheet revision C, the revision in force on the intake date. Work is billed as performed and capped at the NTE; no task proceeds beyond its line amount without a documented change.
4. Assumptions and exclusions
- Permit count is priced at four. The source email estimates three to five; if issuance requires a fifth application, it is added at the rev. C unit price with the change documented against this work order before the work is done.
- Parcel ownership is assumed town-owned per the intake and is confirmed in Task 4 before Task 2 consent work concludes. A privately owned parcel changes the Task 2 basis and comes back as a question, not a silent re-price.
- Permit and recording fees are the utility's cost, invoiced at actuals with receipts, and are not included in the amounts above.
- Construction, materials, inspection, and restoration are excluded from this scope.
5. Deliverables
- Issued permits, executed TUA, documented municipal consent, and the title summary, delivered into the utility's project file as each completes.
- The verification checklist below, attached to this document as shipped.
Prepared and reviewed: Cascade Land Services LLC (fictional)